03.12.2025

Another TPF contract – supervision of the tunnel construction in Rembertów

Tags:

We are pleased to inform you that on 28 November 2025, TPF Sp. z o.o. signed a contract to perform the role of Contract Engineer for the construction of a modern road tunnel in the Rembertów district of Warsaw. This is another project in which our team will supervise the implementation of an investment of this type, further confirming our expertise.

The tunnel will be built under railway line No. 2, along Marsa Street and Gen. A. Chruściel “Monter” Avenue, connecting Old and New Rembertów without the need for a level crossing over the tracks.

Scope of the project:

  • Construction of an approximately 140-meter road tunnel along Marsa Street and Gen. A. Chruściel “Monter” Avenue, along with the removal of the existing railway level crossing.
  • Construction of a two-way Pociskowa Street connected to Ilskiego Street, and extension of Bellony Street to the location of the removed crossing.
  • A roundabout is also planned at the intersection of Marsa Street and Cyrulików Street.

Client: The Capital City of Warsaw, represented by the Municipal Board for City Development (Stołeczny Zarząd Rozbudowy Miasta) and PKP Polish State Railways (PKP Polskie Linie Kolejowe S.A.).

Contractor: A consortium of INTOP SA and INTOP Warszawa (contract value approx. PLN 134 million). 

Project timeline: The works are scheduled to take 29 months. 

Image source: Tunel zamiast szlabanów w Rembertowie - Stołeczny Zarząd Rozbudowy Miasta 

Cooperating with:

EN